|
Human factors for a control room at a new facility |
|
Experience by topic
|
|
2007 - Liquefied natural gas (LNG)
The client was building a new facility, which was to include a new control room. Andy was asked to comment on the engineering contractor's design. He identified a number of deficiencies and was able to advise on how current good practices could be incorporated. He was subsequently asked to provide more detailed advice on the operator interfaces in the control room.
Andy conducted a task analysis workshop with the future operators of the plant. From this he was able to specify requirements for overview and detailed graphics; including task and scenario based displays where appropriate. As well as using the analyses carried out by Andy in the design of their user interfaces, the operators continued to carry out additional task analyses using the same method as they found it a very valuable exercise in reviewing the plant design and considering how they were to operate the plant in the future. |
|
|
Human Hazop for a new plant |
|
Experience by topic
|
|
2007 - Liquefied natural gas (LNG)
The client was in the process of building a liquefied natural gas (LNG) storage facility. As part of its development of a safety report under the COMAH regulations, a human Hazop was carried out. This followed the principles of Hazop, applied to key human activities using a modified set of key words. Because of his knowledge of human factors and LNG facilities he was asked to participate in the Hazop. |
|
Experience by topic
|
|
2006 - Liquified Natural Gas (LNG)
The site had recently undergone extensive modification. This included addition of a new control console in the existing control room. The client recognised that the design of the console had not received sufficient attention, and that the physical ergonomics were not ideal. Andy was asked to evaluate whether process safety had also been compromised through the design. The conclusion was that current best practice had not been followed, and that this meant risks were not as low as reasonably practicable. Andy then used the results of this study to influence the design of a new control room, to be constructed in approximately two years time. He was able to get the principles of ISO 11064 incorporated into the project, including end user participation. |
|
Loss of containment assessment |
|
Experience by topic
|
|
2005 - Liquefied Natural Gas (LNG)
The client was the engineering, procurement and construction (EPC) contractor for a liquefied natural gas (LNG) import, storage and regassification facility being built in Spain. Andy's role was to review the engineering design in order to identify credible loss of containment events and to evaluate the potential consequences. This involved him working with the design team, examining piping and instrument diagrams (P&IDs) and reviewing plant and equipment specifications. His analysis was used to determine the accidental loads that the plant had to be able to withstand so that escalation did not occur. It needed to be presented in a way that the designers could understand and their client would accept. |
|
Development of the Design Accidental Load specification for a LNG storage and export facility |
|
Experience by topic
|
|
2004 - Liquefied Natural Gas
The client was the design contractor for a large Liquefied Natural Gas (LNG) facility to be located in Northern Norway. Following on from the Quantified Risk Assessment of the plant, which Andy was involved in, this project involved assessing the likely consequences of fire and explosion events that may occur. It was necessary to be able to demonstrate that the plant design would mean that it would withstand any of these events that had a frequency above a specified threshold. These were known as the 'Design Accident Loads.' The analysis was used to confirm that appropriate design standards had been used, and that the provision of passive and active fire protection, and emergency shutdown systems were adequate. Andy developed the method for carrying out this analysis, and wrote the report. |
|
|
|